Wednesday, December 9, 2009

Assignment : Case 2

Project Control & Monitoring

Here in this section, you should be recommending to the management of Touprom on how to monitor and control the project to ensure that it will be implemented smoothly and the deliverables can be achieved.


The function of project monitoring is to provide updated information about the project during the implementation stage to the project stakeholders; while the function of the project control is to take actions to steer the project back to the project plan.


Note that in my notes, I have mentioned that project control is important to ensure that:

a.) Project tasks are implemented within the agreed scope

b.) Project is completed within the duration and budget

c.) Project is completed within the expected quality and/or performance requirements

Some of the key words associated with project monitoring & control are:


a.) Milestones

What are the milestones you will need to set up? As previously noted, milestones are incorporated into the overall project schedule to facilitate the control and monitoring of the project. Milestones are usually the major achievements within the project.

In the context of this assignment, milestones can include:

i.) Complete execution of the purchase or rental agreement for the land to site the depot

ii.) Completion of the engineering design of the physical depot

iii.) Handover of the physical depot by the contractor to the client (i.e. Touprom) upon the complete construction, testing and commissioning of the depot

iv.) Completion of the mobilisation of all rental equipment into the depot


b.) Progress reporting - What to report? How to report? Who to report to?

Progress reports are documents that the Project Manager needs to prepare regularly (daily, weekly, fortnightly or monthly) to monitor and communicate the progress of the project to his/her Project Team as well as the client and other stakeholders.

In preparing the progress reports, team members will need to report to the PM on the progress of each of their areas of responsibilities. These information is then combined to produce the overall progress report.

Progress are usually measured as amount of work done and amount of budget spent. These two quantities are also compared with each other to ensure that the budget are spent appropriately.

Real progress of the project will also be measured against the scheduled completion time and cost to see whether the project is ahead of time, on-time or behind time and under-cost, within cost or over-cost.

If the project is behind time, actions must also be highlighted to catch up with the lost time. If the project is over-cost, preemptive measures must also be taken to prevent the project to run out of funds before completion.

Use of graphics such as bar charts is always useful to give a quick representation of the progress.

Monday, December 7, 2009

Question from Your Fellow Student

Question

Hi Mr. Tang
Good afternoon to you.

I would like to ask some info & opinion from Mr. Tang, about our Managing Project - Task 1.
We should use Mr.Tang 's teaching way or use the "Field and Keller" (that Task 1 instruction had mention) or both ways also can, to draw up the activity on the node diagram for Task 1 Question 2 & 3.

Sorry to ask this again because we hear some our classmate, they say that last time their ex-senior was follow Mr.Tang's way to do the activity on node diagram, and they failed this paper in the end.

I would like to apologize & i am not means here to call to account Mr. Tang's teaching way, but just would like to understand more & clearly, as some of us start to worry, as we already finish task 1 in early.

Thanks & best regards.

Reply

Having re-visited the text by Field & Keller and comparing with my lecture notes, I can say that the 'essential methodology' required in the assignment is similar as to what I have presented in the class. These include:

1.) The use the 'Activity-On-Node' or AON method;

2.) The use of forward pass & backward pass to determine all the timings (i.e. EST, LST, EFT, LFT);

3.) The requirement to enter all timings as DAYS, not as dates;

I think the main confusion lies in the way the Activity Box in my notes differ from the Activity Box given in the text.

As you can see from the two types of activity box, the information presented in the activity boxes are exactly the same (i.e. the activity name, duration, EST, LST, EFT, LFT and float).

The difference lies only in the arrangement of the information in each boxes . Moreover, what I call simply as 'float' in my notes are known as 'total float' in the text.

If students feel more comfortable in following the design of the activity box as in the text, you are encouraged to do so. It only involves a change of the design of the boxes, the information is the same. I will leave the choice to you. What is more important is to put in a legend in your diagram to explain what each information means in your boxes so that your answer is concise and clear.

Most of the students from previous batches were using diagrams with the activity boxes I presented in my notes; therefore it is very unlikely that only some failed just because of using activity box of different design from that in the text.

Last but not least, I have mentioned that in the study of Project Management, different books and texts tend to use different diagrams and words to illustrate the same things. As such, it is very easy for students to get themselves confused with the subject.

I hope that this will clarify this query. Please feel free to raise this up in our next lecture if more clarification is required.

Thursday, December 3, 2009

Case 2 : Assignment Framework

Dear Students,

Please note that I have posted slides containing a proposed Assignment Framework for your reference. Refer to the right-top corner of the blog.

I will also add in extra materials in due time.

Good luck,
Tang

Assignment : Case 2

Resource Planning & Project Costing/Financing

Resource Planning


List down the types of resource required for the whole project. Common types of resources can be grouped as:

a.) Finance i.e. $$$$

b.) Human resource

c.) Equipment (general and/or specialised)

d.) Infrastructure

e.) Skills and know-how

f.) Technology


Note that not all resources listed here are applicable for this assignment. Think about it, which is more relevant.

Resources can also be categorized as internal and external. As a general rule of thumb, it is always good practice to use resources that are internally available within your client's organization; because internal resources are cheaper as well as easier to control and monitor. However, diverting internal resources to project work may cause disruption to the daily operations of the company and therefore comes at a cost (called 'opportunity cost').

External resources are sourced outside when they are not available within the organization (e.g. external consultants & contractors). Use of external resources is usually costly, and difficult to control. On the other hand, use of external resources may be cheaper for the company if they are only used one-off for this particular project.

For those of you what wants to take a step further in your assignment, you can write about the pros and cons of using internal vs. external resources in this particular project; and also why you propose to choose one over the other. This allows you to demonstrate to the examiner that you have put the effort to critically think about this assignment.


Project Costing & Financing


Assignment in Case 2 does not provide the budget for the project. You will be required to determine the cost of each individual tasks (again from referring to WBS) and add them up together to get your total budget.

As described during class, there are a number ways you can do the breakdown the costs:

a.) Estimation by percentages (%) of each tasks out of the total budget

b.) Using piece rate e.g. labor (pounds per person-day X no. of persons X no. of days)

You will be expected to write in your report of how the budget will be used. Using charts like bar-chart or pie-chart will probably help the examiner to see better your allocation of costs.


You may also choose to discuss and propose to your client the available means of financing for this project (e.g. internal funding, loan from bank etc.) ; as well as the risks associated with each type of financing. For those of you who are familiar with finance and accounts, you may be aware that there is always a recommended debt-to-equity ratio for companies.